Four stators from Andritz Hydro
Landsvirkjun has signed an agreement with Austrian company Andritz Hydro GmbH for the supply of four stators for Búrfell Hydropower Station. Andritz Hydro will be responsible for their design, manufacture and delivery, as well as supervising installation. The work is scheduled for completion in the first half of 2030.
The total cost of replacing these four stators at Búrfell Hydropower Station is approximately ISK 2.3 billion, with the stators themselves accounting for the largest share of the cost.
Búrfell Hydropower Station commenced operations in 1969, and its stators were first replaced towards the end of the last century. A stator is the stationary part of a generating unit where electricity is produced. It surrounds the generator rotor, whose rotation induces an electric current in the stator windings.