Sigalda Expansion Project
The expansion involves extending the existing powerhouse to the south-west, installing a fourth generating unit and adding a new penstock. The tailrace channel will also be widened near the station. This will increase the station’s installed capacity from 150 MW to up to 215 MW.
The aim is to make the electricity system more flexible and better able to meet peak demand and respond to changes in electricity consumption and generation. The new equipment will also improve efficiency. The expansion will use the existing storage reservoir and will not require any new reservoirs.
Landsvirkjun has awarded contracts to Ístak for earthworks and construction of the main structures, and to DSD Noell for intake racks, water-intake gates and the penstock. Efla will supervise the construction works.
Completion is planned for autumn 2029.