About the Project
The 7,2 MW Qorlortorsuaq hydropower project is in south western Greenland. The project harnesses the outflow of water from a natural lake in the area by constructing a headrace tunnel into the bottom of the lake and raising the lake level by 7 m by a small dam. The headrace tunnel runs 220 m through a hill and is connected to a 280 m long steel penstock, feeding two horizontal axis Francis turbines, in a conventional powerhouse.
A short tailrace canal directs the turbine water to the sea. The harnessed head is approximately 125 m. The project supplies renewable energy to the towns of Narsaq and Qaqortoq by approximately 70 km of 66kV transmission lines.
Services included:
- The procurement of electromechanical equipment.
- The supervision of equipment installation.
- The commissioning and setting up of maintenance and operation programs.
- The training of operators, and operation for the first 5 years.